Middle School/30th Street
Description
Project
El Dorado Middle School/30th Street
Location
El Dorado, KS
Details
- Site Layout
- Worked with architect to meet parking requirements, aesthetics and site efficiency demands
- Drainage
- Designed two dry detention ponds to ensure post-construction runoff was < pre-construction runoff
- Designed onsite storm sewer
- NOI/SWPPP
- Grading
- Terraced entire site to balance earthwork
- Had to account for 30′ of elevation difference across the site
- Provided grading machine control files to contractor to ensure quality control and construction efficiency demands were met
- 30th Street Design
- Worked closely with the City of El Dorado to meet their specifications and standards
- Designed all storm sewer and performed necessary drainage calculations
- Provided grading machine control files to contractor to ensure quality control and construction efficiency demands were met